Utilization

Utilization is the share of available working time spent in active, planned work.

Formula

utilization = active time on planned work ÷ available hours × 100

Reading it

BandRead
70–85%Healthy. Room for meetings, learning, recovery.
<60>Usually process friction, not idleness — check focus time and context switching.
>90% sustainedBurnout and quality risk. Rebalance before someone leaves.

Always look at the per-person spread, not just the team average.

Did you find this article useful?

  • Focus time

    Focus time is the portion of the day spent in uninterrupted blocks long enough for real work — typic...
  • Workload balance

    Workload balance is how evenly active time is spread across a team. What to look at The distributio...
  • Idle vs active time

    The agent distinguishes active time (input or foreground work) from idle time (no interaction). Sess...
  • The weekly and daily views

    Weekly view The default. KPI tiles (average per day, total, change vs last week, top app/category), ...
  • Exporting data

    Most views export to CSV and PDF from the export control on the view. CSV Row-level per person / te...